Revvo Technologies, Inc. v. Cerebrum Sensor Technologies, Inc. (precedential)
A petitioner may take different claim construction positions in district court and at the Board, but it “should explain sufficiently why the different positions are warranted, even in instances that do not implicate Section 112(f).” Simply adopting the patent owner’s district court constructions is not a sufficient reason. The Director vacated the institution decision and remanded.
A petitioner that takes different claim construction positions in its petition and in district court must explain why; simply adopting the patent owner’s district court constructions is not enough, and the duty is not limited to § 112(f) terms. Because the decision clarified the rule, institution was vacated and remanded rather than denied.
Key facts
| Type | Precedential |
|---|---|
| Topic | Institution discretion (§ 314(a)), Review scope and claim construction |
| USPTO subject | AIA – a petitioner must explain why it takes different claim construction positions in the petition and in district court; merely adopting a patent owner’s district court claim construction is not sufficient |
| Decision date | November 3, 2025 |
| Designated | November 3, 2025 |
| Citation | IPR2025-00632, |
| Status | Current |
| Status check | Checked October 14, 2026: still listed as precedential on the USPTO page. Not de-designated. |
Supporting quotes
“The Board also erred when it found that a petitioner is only required to explain its different positions when Section 112(f) is implicated.”
IPR2025-00632, Paper 20, PDF p. 5
“Because this decision clarifies how a petitioner should approach different claim construction positions and how the Office will assess those positions, the appropriate course of action is to vacate the Board’s decision and remand the case to the Board.”
IPR2025-00632, Paper 20, PDF p. 5